Key takeaways
- Plan backwards from the date the bags must be received, not forwards from the enquiry date.
- At LinHord, sampling typically takes 7–10 days and bulk production 25–35 days; each quotation states the schedule for that project.
- Freight, export and import handling and receiving are separate from production time.
- Late artwork, colour changes and resized samples are the usual reasons an approval has to be repeated.
How long do custom bags take to make?
A custom bag lead time is more than the factory’s production time. Count back from the date the bags must be in the warehouse, shop or event venue, then allow for receiving, freight, export and import handling, bulk production, sample approval and artwork preparation. A schedule built forwards from the enquiry date tends to leave out the decisions the buyer still has to make.
LinHord’s published guidance is that sampling typically takes 7–10 days and bulk production 25–35 days. The exact timing depends on the material, construction, artwork and order quantity, and each quotation states the sampling and production schedule for that project. Freight time is separate and depends on the route and transport mode.
| Stage | Main owner | Timing basis |
|---|---|---|
| Artwork and specification | Buyer, with supplier review | Starts when complete files, dimensions and colour references are sent. |
| Sampling | Supplier | Typically 7–10 days at LinHord; confirmed in the quotation. |
| Sample review | Buyer | Sample delivery plus the buyer’s own review and sign-off. |
| Bulk production | Supplier | Typically 25–35 days at LinHord; confirmed in the quotation. |
| Inspection and dispatch | Buyer’s inspector and supplier | The agreed inspection plan and booking date. |
| Freight, customs and receiving | Forwarder, broker, warehouse | Route, transport mode and delivery appointment. |
Know which approvals stop the clock
Schedules usually slip between stages, while a decision is waiting. Artwork supplied as a low-resolution image, a colour changed after the sample, or a new size requested after approval can each mean that the sample step has to be repeated. Give one person authority to approve the sample, and record which revision was approved.
Ask which inputs are needed before the sample can start: vector artwork, Pantone or physical colour references, finished dimensions, handle and gusset measurements, and the logo method. Questions settled in the first enquiry do not have to be answered later, when there is less time left.
| Change | What may need repeating | Record to keep |
|---|---|---|
| Colour changed after sampling | Colour approval, and possibly the sample | New colour reference and date |
| Logo size or position changed | Artwork proof, and possibly the sample | Revised proof with measurements |
| Dimensions or gusset changed | Sample and packing details | Revised specification |
| Material or handle changed | Sample and quotation | Revised quotation and specification |
Does the lead time include shipping?
Production ends when the goods are packed and ready for the agreed handover, not when they arrive. Transit, export and import formalities and the receiving appointment come afterwards and depend on the route, the transport mode and the Incoterm. Compare quotations on the same basis: one may quote a production period, another a delivered date.
If the launch date is fixed, ask whether a split delivery is possible, such as a smaller quantity by a faster mode and the balance by a slower one. Splitting the delivery does not split the order: LinHord’s minimum is 100 pieces per style per colour, and colours cannot be combined to reach it. A split also means a second set of shipping documents and a second receiving event.
Build a working schedule with buffers
Write the schedule as dates, not durations, and mark which dates depend on the buyer. Add a buffer before fixed events such as a trade show, store opening or seasonal launch. Public holidays at origin or destination, carrier capacity and customs checks can move dates outside either party’s control, so the buffer belongs in the plan from the start.
Review the schedule at every approval. If the sample is approved late, move the later dates rather than assuming that production or freight will absorb the delay. A shared schedule with owners and dates also makes quotations easier to compare, because it shows whether each supplier is quoting the same scope.
- The date the bags must be received, and the delivery address
- Quantity for each style and colour
- Artwork status: final files, draft or still in design
- Dimensions or a reference sample
- Preferred Incoterm and transport mode, if already known
Frequently asked questions
Can sampling and bulk production overlap?
Bulk production follows the approved sample, because that sample defines what is made. If time is short, settle material, colour references and artwork as early as possible instead of asking for production to start before the sample is approved.
When should we order for a seasonal launch?
Add up the stages for your route: artwork, sampling, your review, bulk production, any inspection, freight and receiving, plus a buffer. Ask for the sampling and production schedule in the quotation, and confirm the transit time with your forwarder before fixing the order date.
Does the minimum order quantity affect the schedule?
LinHord’s minimum is 100 pieces per style per colour, and colours cannot be combined to reach it. Plan quantities by style and colour before sampling; see the MOQ guide.
Send the date the bags must be received, the delivery address, quantities by style and colour and the current artwork status. We will confirm the sampling and production schedule in the quotation.